2020 Working Parties
(Note that clicking on a small picture will show that picture larger)
(All photos © John & Sandra Lawson, unless otherwise shown)
Click on a link below to go directly to that month (or just scroll down)
January February March April May June July August September October November
Thursday 16th January 2020 – Our first work party of the New Year, and nine volunteers attended on a dry, overcast morning to complete work on Lock 66 (Wheelock Lower) by finishing the painting of the top gates . The majority of the team moved up to concentrate on preparing Lock 65, scraping paddle gear, balance beams and fittings, strapping posts and bridge rails. We did manage to apply some paint to the metalwork before rain halted proceedings (as forecast) at lunchtime. An early finish but a worthwhile day, nevertheless.
Painting Top Balance Beam on Lock 66 | Painting Metal Safety Strip on Top Gate |
(Photos: Jane Hargreaves)
Thursday 20th February 2020 – Cancelled because of forecast bad weather.
Thursday 19th March 2020 – Cancelled by CRT because of the Covid-19 outbreak.
Thursday 16th April 2020 – Cancelled by CRT because of the Covid-19 outbreak.
Thursday 21st May 2020 – Cancelled by CRT because of the Covid-19 outbreak.
Thursday 18th June 2020 – Cancelled as CRT still won’t let us resume work.
Thursday 16th July 2020 – Cancelled as CRT still won’t let us resume work.
NOTE: CRT have indicated that future work parties should be limited to six volunteers per group. Given our usual numbers of around 10-12, we would have to divide into 2 teams. Depending on our location, the teams could work on the same day or a different day to suit. More details to follow, but we hope to be allowed to resume with our August working-party.
Tuesday 21st July 2020 – A “trial” work-party took place to try out a whole new set of Covid-19 related Health and Safety rules, and safe methods of working to incorporate social distancing. It had to be limited to 3 invited volunteers + 1 from CRT so that it could be carefully controlled and evaluated. We had to work without sharing tools, brushes etc. and make sure that there was only one person on each gate, railing etc. at any one time. Given good weather and not too many boats coming through, we completed a good amount of work including painting the new top gate towpath side on Lock 52 at Church Lawton.
Thursday 20th August 2020 – Finally a real work-party at Lock 65 took place (with “social distancing” in effect). The main job was the railings surrounding the by-wash. Twelve (of the 21) sections of the railings were scraped to bare metal and white Hammerite paint applied. The mixed hedge around the by-wash was trimmed back and the concrete apron cleared of all moss and vegetation. All three lock ladders were prepared and painted (by Margaret who had rubbed down the first one at our previous working party in January!). Towpath side vegetation was trimmed along the hedge and strapping posts. The whole area was cleared of litter.
Scraping Railings | Painting Railings |
Where we got to (9 to go) | Painting the Lock Ladders |
Photos (right column): Roger Evans
Thursday 17th September 2020 – Seven volunteers spent the day at Lock 65. The remaining 9 sections of the railings around the by-wash were scraped to bare metal and two coats of white Hammerite paint applied. All three lock ladders were painted with a second coat. The mixed hedge behind the by-wash (and beyond) was trimmed back and topped, and the towpath-side vegetation was trimmed. Also the balance beams on the bottom gates of the offside chamber were prepared and painted.
Starting on the other 9 railings | Trimmed Hedge behind bywash | Nearly finished painting |
Thursday 21st October 2020 – Eight volunteers this month on a dry and reasonably warm day. A further coat of white Hammerite paint was applied to the remaining nine sections of by-wash rail. The bottom gates on the offside lock chamber were prepared and painted including the paddle gear and beams. The bridge rails were scraped and painted. Four strapping posts were prepared and painted. The rails on the top gates of both chambers and the paddle gear was scraped and painted. Some additional painting was completed on Lock 66 (mooring posts and top gates). Finally the area was cleared of litter.
Thursday 19th November 2020 – A dry day meant that we were able to finish off the painting and declare that locks 65 and 66 were complete at last.
Click on a link below to go directly to that month (or just scroll back up)
January February March April May June July August September October November
Previous year (2019) | Cheshire Locks Index | Next Year (2021) |